Deloitte: what is stalling Canada's $1 trillion infrastructure ambition?

Deloitte points at the front end of the pipeline and proposes a $5 billion fund to clear the bottleneck

Deloitte: what is stalling Canada's $1 trillion infrastructure ambition?

Private investment reaching final investment decision on Canadian infrastructure projects could roughly triple, from about $65bn to as much as $191bn, under a proposed Early Projects Office (EPO).  

The estimate comes from a Deloitte Canada report released today, covering a subset of modelled projects from the Canada Investment Summit Prospectus, part of the federal government's ambition of unlocking approximately $1tn in infrastructure investment over five years. 

Deloitte puts the EPO scenario $94bn above the status quo in additional real GDP, with support for an average of 40,700 jobs a year over 10 years and $22bn in new federal government revenues. 

The EPO would take on early development work, including business-case analysis, regulatory and permitting work, front-end engineering, commercial development, Indigenous and community engagement, market development and financial modelling, advancing projects simultaneously rather than sequentially.  

Deloitte recommends housing it within the Canada Infrastructure Bank, drawing on the Bank's project finance capabilities, lifecycle expertise and investment systems. 

Jordan Eizenga, national infrastructure and real estate leader at Deloitte Canada, said the country holds both the ambition and the project pipeline to build infrastructure on a scale unseen in decades.  

An Early Projects Office, Eizenga said in the report, could pull partners, evidence, and expertise together sooner, so projects become "investable faster" and governments and investors decide on firmer footing. 

Deloitte proposes a $5bn government-funded Early Development Fund to pay for early-stage work.  

A portfolio approach would let related projects be developed in "pods" that share enabling infrastructure, create markets, use risk-sharing finance and build partnerships by design. 

The report identifies 12 prospective pods, including Arctic access, Atlantic clean power, rare earths, sustainable aviation fuel and defence-related infrastructure, several of which sit in the sectors advisors have watched most closely this year. 

Deloitte reviewed all 167 projects in the Prospectus and identified 57 that could benefit directly from an EPO.  

For about one-third of those, the report says the office could be the deciding factor in making them investable.  

The 57 need more than capital, with barriers including missing shared infrastructure, undeveloped markets, first-of-a-kind technology and complex partnerships. 

The office could cut in half the average time from project idea to final investment decision and lower early development costs, according to Deloitte.  

Investment could begin in 2027, and by 2030 two-thirds of the modelled portfolio could be moving forward, three to four years sooner than under the status quo, a timeline that shapes how portfolio managers approach domestic infrastructure exposure. 

"Building faster does not mean lowering standards for Indigenous consultation, environmental review, engineering or labour," said Jürgen Beier, National Infrastructure Technology Leader at Deloitte Canada, in the report. 

Nearly 100 additional projects outside the Prospectus could also benefit, including provincial, Indigenous-led, health, Crown corporation and utility projects.  

Deloitte calls its estimates conservative, noting they exclude development spending preserved by stopping weak projects earlier and the benefits of projects outside the Prospectus. 

The figures reflect 54 of the 57 projects identified. The other three were excluded for lacking enough cost information to be valued, alongside the firm's broader reading of the Canadian capital markets outlook. 